Ipava Avenue & 192nd Street Improvements

The City of Lakeville is proposing to reconstruct Ipava Avenue from Kenwood Trail (County Road 50) to 192nd Street along with 192nd Street from Kenwood Trail to Ipava Avenue in 2022. This project includes pavement reclamation, spot curb and gutter replacement, storm sewer repairs and water and sewer system improvements.

Helpful Information

Project Timeline

  • October 18, 2021: City Council approves feasibility report
  • November 11, 2021: Neighborhood meeting (see below)
  • November 15, 2021: First public hearing (improvement hearing)
  • November 2021 – January 2022: Prepare plans and specifications
  • February 2022: Receive bids
  • April 2022: Assessment hearing
  • June – August 2022: Construction

Neighborhood Meeting

November 11, 2021
6-7 p.m.
Lakeville City Hall
20195 Holyoke Avenue

Contact Us

If you have any questions regarding the project, contact Alex Jordan, Assistant City Engineer, at 952-985-4503 or by email.