2021 Park Bond Referendum Progress Report
Last Content Update:
Get updates on the park projects included in the $38 million 2021 Park Bond Referendum that was approved by voters. The Status column will show:
- In process
- Completed
- Future
Check back for updates to this page as they are available.
Project description | Update | Status | ||
---|---|---|---|---|
Improve Antlers Community Park: Add parking, trail loop system, modern restroom facilities, picnic shelters, volleyball courts and more. You can find more details on our Park Improvements and Updates webpage. | Park construction is underway and is scheduled to be completed by early 2024 | In process | ||
Improve Ritter Farm Park: Renovate and expand existing cabin to enhance nature-based programming, including site improvements. | This project was completed in late August 2023 and a grand opening will be held on October 14, 2023. This event is open to everyone - please RSVP online. | Completed | ||
Construct outdoor public multi-use pavilion at Hasse Arena: This outdoor refrigerated covered ice rink will allow for programmed and public open skating and hockey, and activities such as boot and pond hockey and outdoor tournaments, in winter months. During the off season, the pavilion would be used for trade shows, community events and concerts, and other large gatherings. You can find more details on our Park Improvements and Updates webpage. | Bids for the ice plant and new outdoor ice rink portion of the project will be awarded in September. This portion of the project includes a new refrigeration ice plant to operate both the indoor rink and outdoor rink; the outdoor rink subfloor piping system and rink floor surface; and the rental of a temporary chiller that will allow ice to be maintained inside during the spring, late summer and fall months while the current ice plant is under construction. The site work and roof structure construction for the project was re-bid in fall of 2022. Construction commenced in Spring of 2023 and construction is on schedule to be completed by January 2024. | In process | ||
Replace basketball courts | Basketball courts at Bassett, Foxborough, Greenridge, Highview, Hypointe Crossing and Rolling Oaks parks have been replaced. | Completed | ||
Improve the Lakeville Area Arts Center facility | Construction of the Arts Center loading dock and new office space was completed in June 2023. | Completed | ||
Trail gaps/connectivity: Build new and connect existing trails throughout the City. You can find more details on our Park Improvements and Updates webpage. | Construction of trail segments began in 2023 and will continue into 2024. | In process | ||
Replace park ID signs | Installation of landscaping and 39 ID signs has commenced and will be completed by fall of 2023. | Completed | ||
Construct Avonlea Community Park: Includes splash pad, challenge course, pickleball courts, trails, multi-purpose athletic fields, baseball field and playground. You can find more details on our Park Improvements and Updates webpage. | Planning and design proposed to occur in 2023 with construction in 2024. | Future | ||
Develop East Community Park Phase II: Add canoe and kayak racks, modern restroom facilities, trailhead and shelter, open lawn play area, and native prairie areas. You can find more details on our Park Improvements and Updates webpage. | Planning and design proposed to occur in 2024 with construction in 2025. | Future |