2023 Miscellaneous Roadway Repairs and Overlays Project

The City of Lakeville is proposing to resurface asphalt pavement on approximately two miles of residential streets in 2023. This project includes pavement milling and overlay, partial curb replacement and some storm sewer repairs.

Project Timeline

  • Fall 2022: Preliminary engineering
  • Winter 2022/2023: Final design
  • March 9, 2023: Bids were received and publicly opened
  • April 3, 2023: City Council awarded project to McNamara Contracting, Inc.
  • April 25, 2023: Keystone Avenue drain tile installation
  • May 1-20, 2023: Construction
    • May 1-6: Removals and concrete work
    • May 8-13: Removals, concrete work, milling and turf restoration
    • May 15-20: Paving and turf restoration
    • Note: Schedule subject to change

Helpful Documents

Contact Us

If you have any questions regarding the project, contact Michael Kutz, Graduate Engineer, at 952-985-2796 or by email.